Skip navigation

LNG Gas Storage Facility – Pretreatment System Upgrade

Confidential Client | Newport, OR

Project Overview

This project focused on enhancing the pretreatment system for CO2 and water removal at an LNG storage facility to process 6.5 MMSCFD of natural gas. The upgrade involved integrating new heat exchangers and a compressor to improve system performance and operability.

Key Highlights

- Designed the integration of multiple heat exchangers and a compressor into the existing system. 

- Conducted equipment reviews, piping layout, and control valve sizing and selection. 

- Developed comprehensive documentation, including P&IDs, equipment lists, piping specifications, valve lists, PSV list, instrument index, and data sheets. 

Results

The upgraded pretreatment system offers improved functionality, reliability, and operational efficiency, ensuring the facility meets stringent operational standards. Our detailed engineering approach ensured seamless integration and long-term performance.

More Projects

See what we can do for 
your next project