Combined Cycle Plant Water Treatment Upgrade

Southern Power Company | Plant Franklin

Project Overview

To meet increased water demand from a third generating unit and steam augmentation, the Plant Franklin WTP was upgraded to ensure reliable, cost-effective capacity expansion. Originally designed in 2001, the plant now supplies approximately 1,000 GPM of condensate makeup water through comprehensive system enhancements.

Key Highlights

- Replaced the original clarifier with an advanced ultrafiltration membrane system. 

- Added two new 2-pass RO trains, increasing capacity by 500 GPM. 

- Installed two degasifiers and two mixed-bed demineralizers for improved water quality. 

- Upgraded downstream operations with new sludge thickener tanks and bypass lines for seamless integration. 

- Removed aging equipment, including multimedia filters, clarifiers, and sludge tanks, to modernize the facility.

Engineering Support

Harris Group provided end-to-end services including preliminary design, detailed engineering, capital cost estimation, and construction support. The multi-disciplinary team ensured a robust, efficient upgrade aligned with operational needs.

Outcome

Enhanced capacity and operational reliability, supporting the plant’s expanded power generation requirements and ensuring long-term water treatment efficiency.